Dangote Oil Refinery To Begin Installation Of Equipments

Dangote Oil Refining Company Limited has said the installation of equipment for the crude oil refinery being built in Lagos will begin this month.

The Head, Quality Assurance/Quality Compliance and Construction, DORC, Mr. Rama Putta, told our correspondent, who visited the site of the plant, that the 650,000-barrels-per-day refinery would come on stream by September 2019.
According to him, the basic engineering work has reached 98 per cent completion; the detailed engineering, 90 per cent; 3D modelling, 80 per cent; long lead items ordering, 100 per cent; bulk plates ordering, 90 per cent; equipment and bulk items, 50 per cent; and construction activities, 25 per cent.

He said the sand filling of the site was completed six months ago, adding that 60 per cent of the land was swampy.

Putta said bringing the land to three metres above the mean sea level was the biggest challenge, adding, “The sand is tightly compacted and ready for the erection of the equipment. No flood can affect our area. The surrounding area is only one metre above the mean sea level. The entire Lagos is only 1.5 metres above the main sea level.

“We dredged sand from the Atlantic Ocean, about 60 million cubic metres. The world’s biggest dredgers dredged the sand for about 18 months. It’s a big job and is completed successfully. Now, what is left is to erect the equipment.”

Read More

Rayo
Hi, My name is Mo-Rayo. You are welcome to my Blog where I dish out daily news ranging from politics, celebrity gist and gossip, health and fashion tips and lots more that you'd get to find out when you stick with me. I'm pretty simple, fun to be with, lover of adventure and other secret thigs like Indian songs. Welcome once again to my World